STEAM TEMPERATURE CONTROL STRATEGY FOR PIPE-BLOWING BY USING STEAM UNDER CONDITION WITHOUT BOILER WATER CIRCULATING PUMP FOR ULTRA-SUPERCRITICAL 1 000 MW UNIT
Thermal Power Generation   Vol. 40, Issue 5, Pages: 69-72(2011)
更新时间:2025-09-28
    • STEAM TEMPERATURE CONTROL STRATEGY FOR PIPE-BLOWING BY USING STEAM UNDER CONDITION WITHOUT BOILER WATER CIRCULATING PUMP FOR ULTRA-SUPERCRITICAL 1 000 MW UNIT

    • CLC: TK223.7
    • Published:2011

    移动端阅览

  • LI Xinhu Guangzhou Yueneng Electric Power Science and Technology Development Co Ltd. STEAM TEMPERATURE CONTROL STRATEGY FOR PIPE-BLOWING BY USING STEAM UNDER CONDITION WITHOUT BOILER WATER CIRCULATING PUMP FOR ULTRA-SUPERCRITICAL 1 000 MW UNIT[J]. Thermal Power Generation, 2011, 40(5): 69-72. DOI:

  •  
  •  
icon
试读结束,您可以激活您的VIP账号继续阅读。
去激活 >
icon
试读结束,您可以通过登录账户,到个人中心,购买VIP会员阅读全文。
已是VIP会员?
去登录 >

0

Views

140

下载量

1

CSCD

Alert me when the article has been cited
提交
Outline
No Sections

Related Articles

ANALYSIS AND OPTIMIZATION OF RUN BACK CONTROL STRATEGY FOR ULTRA-SUPERCRITICAL 1000 MW UNIT
ANALYSIS AND DISPOSAL OF PROBLEM FOR CARRYING BIG GRAINS INTO COAL PULVERIZING SYSTEM OF 1000 MW ULTRA-SUPERCRITICAL UNIT
STUDY ON CONSTRUCTION OF HEAT RELEASE SIGNAL FOR ULTRA-SUPERCRITICAL UNITS
SCALING ON THROTTLE PLATE OF THE WATER-WALL IN BOILER FOR ULTRA-SUPERCRITICAL UNIT AND DISPOSAL THEREOF
CONTROL MEASURES FROM BOILER SIDE IN LOAD REJECTION TEST OF SUPERCRITICAL 600 MW UNIT

Related Author

CHEN Xiaoqiang
LUO Zhihao
YIN Feng Zhejiang Provincal Electric Power Testing and Research Institute
WANG Xin-ge
LI Hong-tao
LIANG Mao-chun Huadian Zouxian Power Plant
SUN Qun-li
LI Jia-chuan

Related Institution

Zhejiang Electric Power Test and Research Institute
Huadian Zouxian Power Plant
College of Energy and Power Engineering, North China Electric Power University
Huaneng Yuhuan Power Plant
North China Electric Power Research Institute (Xi'an) Co., Ltd
0