SEVERAL PROBLEMS NEEDING TO PAY ATTENTION FOR CHEMICAL SUPERVISION IN CAPITAL CONSTRUCTION COMMISSIONING OF SUPERCRITICAL 600MW UNIT
Thermal Power Generation   Issue 10, Pages: 59-62(2007)
更新时间:2025-09-28
    • SEVERAL PROBLEMS NEEDING TO PAY ATTENTION FOR CHEMICAL SUPERVISION IN CAPITAL CONSTRUCTION COMMISSIONING OF SUPERCRITICAL 600MW UNIT

    • DOI:10.19666/j.rlfd.2007.10.017    

      CLC: TM621
    • Published:2007

    移动端阅览

  • DAI Chuan-long, DIAO Bao-shengGuodian Changzhou Power Generation Co Ltd. SEVERAL PROBLEMS NEEDING TO PAY ATTENTION FOR CHEMICAL SUPERVISION IN CAPITAL CONSTRUCTION COMMISSIONING OF SUPERCRITICAL 600MW UNIT[J]. Thermal Power Generation, 2007, (10): 59-62. DOI: 10.19666/j.rlfd.2007.10.017.

  •  
  •  
icon
试读结束,您可以激活您的VIP账号继续阅读。
去激活 >
icon
试读结束,您可以通过登录账户,到个人中心,购买VIP会员阅读全文。
已是VIP会员?
去登录 >

0

Views

144

下载量

3

CSCD

Alert me when the article has been cited
提交
Outline
No Sections

Related Articles

CONTROL OPTIMIZATION OF MAIN AUTOMATIC REGULATING SYSTEMS FOR HOME-MADE SUPERCRITICAL 600 MW UNIT
APPLICATION OF PLANT-LEVEL SUPERVISORY INFORMATION SYSTEM FOR SUPERCRITICAL UNIT IN YAOMENG POWER PLANT
ANALYSIS OF OVER-TEMPERATURE ON THE PLATEN SUPERHEATER OF ONCE-THROUGH BOILER FOR SUPERCRITICAL 600 MW UNIT
ANALYSIS OF RUNBACK FUNCTION TEST IN SHANWEI POWER PLANT
OPTIMIZATION OF CONTROL STRATEGY FOR SUPERCRITICAL 600 MW UNIT WITH SMALLER CROSSAREA OF PRIMARY AIR DUCT

Related Author

ZHU Xiao-xing
XUN Xin
WANG Bai-chun
LIU Wu-lin
LI Jing-baiHunan Provincial Electric Power Testing & Research Institute
ZHANG Yi1
LI Yu-peng1
WU Tao21.Yaomeng Power Generation Co Ltd No.2

Related Institution

Hunan Electric Power Test and Research Institute
Yaomeng Second Power Generation Co., Ltd
Xi'an Thermal Power Research Institute Co., Ltd
Yuedian Jinghai Power Generation Co., Ltd
Guangdong Honghai Bay Power Generation Co., Ltd
0